Construction Course of the Bird’s Nest----2008 Beijing Olympic Main Stadium

2008/11/7/18:22 来源:慧聪工程机械网

  The Olympic Project Management Office was established by Beijing City Planning Commission in April 2002 to take special charge of organization and coordination of project legal person bidding on Olympic stadiums together with associate facilities in addition to formulation of various bidding documents, so as to energetically release and introduce project legal person bidding of Olympic stadiums throughout the world.

  The public offering of project prequalification and intention collection documents all over the world began in October 2002. Meanwhile, an international competition on Design Scheme of Architectural Concept on 2008 Beijing Olympic Main Stadium was convened in Beijing. After the prequalification of design entrants or combos, 7 independent entrants and 7 combos of such countries and regions as China, U.S., France, Italy, Germany, Japan and Australia participated in the competition for conceptual design scheme.

  After the evaluation and recommendation of the 7 application documents on National Stadium project legal person by Evaluation Committee and approval by the Beijing municipal government between January and February 2003, 5 legible applicants were given admission into the second phase of project legal person bidding.

  Through strict evaluation procedure and majority vote, the Nest scheme of novel design and unique structure jointly designed by Swiss Herzog - Demeilong Design Company, Ove Arup & Partners Hong Kong Ltd. and Design Combo of China Architecture Design & Research Group was finally chosen in April 2003. Meanwhile, the tendering document for the cooperator of National Stadium project legal person was formally awarded.

  The comprehensive evaluation on optimized design, construction, financing, operation and handover schemes delivered by the bidder of project legal person cooperator was carried out in June 2003. Two candidates ranking top in comprehensive scores were recommended by the Evaluation Committee in July 2003.

  After the negotiation and then approval by the Beijing municipal government, the CITIC Combo consisting of CITIC, Beijing Urban Construction Group Co., Ltd., Guoan Yueqiang Co., Ltd. and Golden State Holding Group Corporation became the successful bidder of the said project in August 2003.

  The Authority Agreement on National Stadium project of 2008 Beijing Olympic Main Stadium was concluded between CITIC Combo (viz. the successful bidder) and Beijing municipal government, National Stadium Agreement between Beijing municipal government and Olympic Organizing Committee, and Cooperative Operation Contract between Beijing municipal government and Beijing City State-owned Assets Operation Co., Ltd. on August 9, 2003.

  Beijing City State-owned Assets Operation Co., Ltd. and CITIC Combo launched formal start of various preparations on the said project in September 2003. The Design Service Contract of National Stadium was concluded between National Stadium Co., Ltd. and Design Combo of Swiss and China in November 2003.

  The construction of the National Stadium commenced at 9:15 (a.m.) of December 24, 2007 with Deputy Secretary of CPC Beijing Municipal Committee, Acting Mayor of Beijing City, and Executive President of Beijing Olympic Organizing Committee, Mr. Wang Qishan presiding over the commencement ceremony, where Mr. Liu Qi gave an ardent address. He said that the magnificent National Stadium would become a symbolic building of exhibiting new Olympic image and making use of concerted wisdom of domestic and oversea architectural designers, and its construction was the key symbol of overall construction of Beijing Olympic stadiums and also an important milestone in the preparations of 2008 Beijing Olympic Games.

  As the symbolic athletic building in China and Beijing Olympic, the National Stadium was listed as the main stadium. It sits in Beijing Olympic Park and also at the eastern side of the north end along Beijing City middle axial line, with a floor space of 0.204 million m2, building area of 0.258 million m2 and admitting 0.1 million audience, including 0.02 million temporary seats, which had been completed by the end of 2006. It would undertake a number of essential activities and key competitions including opening and closing ceremonies, track and field contests as well as men football final during the 2008 Olympic Games. After the Beijing Olympic Games, it will become the venue of sports competition and various non-competition activities, and additional large-sized special venue for citizens to attend sports and other recreational activities.

  Its design scheme was available by means of global design bidding. Through fierce competition, the Nest scheme jointly designed by Swiss Herzog - Demeilong Design Company, Ove Arup & Partners Hong Kong Ltd. and Design Combo of China Architecture Design & Research Group finally became the winner.